university of southern california Operations And Supply Chain Management Assignment Help - standard cost
Question - Morro Bay Surfboards manufactures fiberglass surfboards. The standard cost of direct materials and
direct manufacturing labor is $225 per board. This includes 30 pounds of direct materials, at the
budgeted price of $3 per pound, and 9 hours of direct manufacturing labor, at the budgeted rate of
$15 per hour. Following are additional data for the month of July:
Units completed 5,500 units
Direct material purchases 190,000 pounds
Cost of direct material purchases $579,500
Actual direct manufacturing labor-hours 49,000 hours
Actual direct labor cost $739,900
Direct materials efficiency variance $ 1,500 F
There were no beginning inventories.
REQUIRED
1. Compute direct manufacturing labor variances for July.
2. Compute the actual