Explore our Solution Library

: 2754 276 0 4 0 0

Florida Atlantic University Operations And Supply Chain Management Assignment Help - the critical path


Question - 5) Given the critical path below, calculate the following
a. The crash cost per unit time savings for each activity.
b. The maximum total crash time savings and cost.
c. The maximum total time-savings with a $3000 budget.
Activity Normal Time Normal Cost Crash Duration Crash Cost
A 8 days $8,000 7 days $12,000
B 5 days $2,000 3 days $10,000
C 10 days $9,000 9 days $12,000

Solution Preview - No Solution Preview Available

Original Question Documents

N/A

Found What You Need?

Scroll down to find more if you need to find our more features

Place Your Order